Overpass Project Update: June 2020
Despite the pandemic and the Governor’s lock-down order, Milestone Contractors has continued working on the project and they are making great progress. They are meeting and exceeding the project’s very aggressive schedule. We are now [...]
The Republic: Laying the Foundation, Crews set path of new railroad overpass
Milestone Contractors construction crews are continuing to make progress on the railroad overpass and interchange project on Columbus’ west side that will allow motorists to avoid being stopped by railroad traffic at the intersection of State Road 46 and State Road 11.
Overpass Project Update: February 2020
Construction crews continue to make significant progress on the construction of the railroad overpass on State Road 46.
Overpass Project Update: January 2020
Heavy rain earlier this month has not significantly delayed construction work on the railroad overpass and interchange project on Columbus’ west side, although change orders have slightly impacted the cost of the project.
Overpass Project Update: December 2019
Crews from Milestone Contractors have been working seven days a week — and, at times, past daylight hours — on the estimated $35 million project that is being jointly funded by the Indiana Department of Transportation, City of Columbus, Bartholomew County, Cummins Inc. and the Louisville and CSX Railroads.
City Breaks Ground on Long Awaited Railroad Overpass
A project nearly four years in the making is now a reality after city, state and railroad officials broke ground on November 4, 2019 for an estimated $35 million railroad overpass on Columbus’ west side.