Heavy rain earlier this month has not significantly delayed construction work on the railroad overpass and interchange project on Columbus’ west side, although change orders have slightly impacted the cost of the project.

The $35 million overpass being built at State Road 46 and State Road 11 on Columbus’ west side will prevent traffic from being stopped at the railroad crossing there as train traffic increases on the Louisville & Indiana tracks. Construction on the project began in November and is expected to be completed by spring 2021, although landscaping and other finishing work will continue through 2021.